[Nov-2021] SAP C-TS412-1909 Dumps - Secret To Pass in First Attempt
SAP C-TS412-1909 Exam Dumps [2021] Practice Valid Exam Dumps Question
SAP C-TS412-1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
| Resources > 12% | Describe how the Resource Planning process integrates with HCM |
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Material > 12% | Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
SAP C-TS412-1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 29
What are the prerequisites for resource-related billing? Note: There are 2 correct Answers to this question.
- A. Released WBS elements, activities, and/or activity elements
- B. An activity-account-assigned network that is assigned to a sales order item
- C. A header-account-assigned network that is assigned to a sales order item
- D. A dynamic item processor (DIP) profile with the appropriate settings
Answer: A,D
NEW QUESTION 30
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Investment profile
- B. Results analysis key
- C. Costing sheet
- D. Settlement rule
Answer: C
NEW QUESTION 31
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Project simulations can create purchase requisitions.
- B. Multiple project simulations can be used simultaneously.
- C. Project simulations can be used to plan structures and costs.
- D. Project simulations allow posting of actual data.
- E. Project simulations can be created without using an operational project as a template.
Answer: B,C,E
NEW QUESTION 32
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Milestone
- B. Network header
- C. Activity
- D. Activity element
Answer: C
NEW QUESTION 33
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
- A. Forward
- B. Current date
- C. Only capacity requirements
- D. Backward
Answer: D
NEW QUESTION 34
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Control key of an activity
- B. Capacity planner group in the network header
- C. Scheduling and distribution key
- D. Scheduling and capacity category
Answer: A
NEW QUESTION 35
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct Answers to this question.
- A. The network is assigned to a sales order item.
- B. A procurement indicator must be assigned to the activity.
- C. The material master of the component must permit project stock management.
- D. The Project Stock indicator is set in the project definition (non-valuated or valuated).
- E. The network activity is assigned to a WBS element.
Answer: B,C,D
NEW QUESTION 36
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.
- A. Document information records
- B. Basic dates for activities
- C. Material components
- D. Relationships
- E. Internally processed activities
Answer: C,D,E
NEW QUESTION 37
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Network activity
- B. BOM item
- C. Material master
- D. WBS element
Answer: A,B
NEW QUESTION 38
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct Answers to this question.
- A. You can always maintain the actual start and finish date of a WBS element.
- B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released".
- C. You can only maintain the actual start of a WBS element if the finish date is not maintained.
- D. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released".
Answer: B,D
NEW QUESTION 39
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Results analysis
- B. Settlement
- C. Milestone trend analysis
- D. Confirmations
- E. Progress analysis
Answer: A,B,E
NEW QUESTION 40
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
- A. Sales order
- B. Inquiry
- C. Billing
- D. Quotation
Answer: A,D
NEW QUESTION 41
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material master is set to external procurement.
- B. The material is assigned to the activity as a non-stock material.
- C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
- D. The availability check for material components indicates missing parts.
Answer: C,D
NEW QUESTION 42
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a purchase order
- B. Saving a supplier invoice
- C. Saving a service entry sheet
- D. Saving a goods receipt
Answer: C,D
NEW QUESTION 43
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching for the individual status
- B. By searching via status combination code
- C. By searching via status selection profile
- D. By searching for the status profile
Answer: A,D
NEW QUESTION 44
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Maintenance orders assigned to an activity
- B. Project-relevant purchase orders
- C. Production orders assigned to WBS elements
- D. Capacity requirements
Answer: A,D
NEW QUESTION 45
You are using networks and external activities in your project. The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- B. Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling
-> Purchase order monitoring -> Goods receipt -> Invoice receipt - C. Vendor selection -> Purchase order handling -> Invoice receipt -> Purchase order monitoring -> Goods receipt
- D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
Answer: D
NEW QUESTION 46
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
- A. Cost element report on budget updates
- B. Line item report for budgets
- C. Structure overview for budgets
- D. Hierarchical report on budget updates
Answer: B
NEW QUESTION 47
What functionality can you perform with activity elements?
- A. Assign material
- B. Assign work centers and capacities
- C. Schedule WBS elements
- D. Create relationships
Answer: D
NEW QUESTION 48
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Third-party order
- B. Purchase requisition and Reservation for WBS element
- C. Preliminary purchase requisition for WBS element
- D. Planned order
- E. Reservation for WBS element
Answer: B,C,E
NEW QUESTION 49
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Planned revenue requires a sales order assigned to a WBS element.
- B. Actual revenue is posted via a billing plan assigned to a WBS element.
- C. Actual revenue is posted via a billing document created from a sales order
- D. Planned revenue can be transferred from a sales quotation.
Answer: C,D
NEW QUESTION 50
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Plant
- B. Sales organization
- C. Controlling area
- D. Operating concern
- E. Company code
Answer: A,C,E
NEW QUESTION 51
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Parameters for the network type
- B. Network profile
- C. Network type
- D. Project profile
Answer: A
NEW QUESTION 52
......