NEW QUESTION 42
Which object is used to allocate the costs from a claim to the project structure?
- A. WBS element
- B. Internal order
- C. Claim
- D. Network activity
Answer: D
NEW QUESTION 43
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?
- A. Milestone
- B. Activity element
- C. Network header
- D. Activity
Answer: D
NEW QUESTION 44
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Investment profile.
- B. Results analysis key
- C. Costing Sheet
- D. Settlement rules
Answer: D
NEW QUESTION 45
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. The system automatically creates a new purchase requisition with the difference to the original quantity.
- B. A workflow can be triggered to inform the purchasing group.
- C. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
- D. The purchase order is updated automatically to match the new quantity while saving the project.
Answer: B
NEW QUESTION 46
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.
- A. Project definition
- B. WBS elements
- C. Milestones
- D. Sales order items
Answer: B,D
NEW QUESTION 47
To which object can you assign a factory calendar?
- A. Milestone
- B. Material component
- C. Network header
- D. Relationship
Answer: D
NEW QUESTION 48
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.
- A. The maximum size of a free float is as large as the total float of an activity.
- B. Float time can be negative.
- C. By default, critical activities have a float time, which is less than or equal to zero.
- D. Activities with the time constraint "Must start on" always have a negative float time.
- E. The float time of WBS elements is calculated by extrapolation.
Answer: B,C,D
NEW QUESTION 49
You are working with networks and WBS elements. Which of the following statements applies
- A. You can assign the network header to multiple WBS elements
- B. You can reassign an activity from one network to another
- C. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
- D. You have to maintain a network profile in the project profile
Answer: C
NEW QUESTION 50
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question
- A. Standard network with activities
- B. Assignment between material and standard network
- C. A production order
- D. A material master with sales views
- E. A bill of material with sales views
Answer: A,B,D
NEW QUESTION 51
Which report can use user-specific layouts?
- A. Cost element report
- B. Line item report
- C. Hierarchical report
- D. Enhanced individual overview
Answer: D
NEW QUESTION 52
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Milestone trend analysis
- B. Progress analysis
- C. Settlement
- D. Results analysis
- E. Confirmations
Answer: B,C,D
NEW QUESTION 53
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.
- A. WBS elements
- B. Network header for activity-account-assigned networks
- C. Standard WBS elements
- D. Network activity for activity-account-assigned networks
Answer: A,B
NEW QUESTION 54
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
- A. Forward
- B. Backward
- C. Current date
- D. Only capacity requirements
Answer: B
NEW QUESTION 55
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.
- A. Relationships
- B. Basic dates for activities
- C. Internally processed activities
- D. Material components
- E. Document information records
Answer: A,C,D
NEW QUESTION 56
Project structure.
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?
- A. You can use an indicator to determine that only coded project numbers may be used within the project system.
- B. You can use only numbers for a project coding mask definition.
- C. The standard project definition must differ from the definition of the operative project.
- D. You can create project coding mask X... event if there are project numbers beginning with X.
Answer: A
NEW QUESTION 57
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Requirements type
- B. Requirements class
- C. Schedule line category
- D. Item category
Answer: D
NEW QUESTION 58
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Resource reports
- B. Cost element reports
- C. Structure information system reports
- D. Hierarchical reports
Answer: C
NEW QUESTION 59
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question
- A. Resource reports
- B. Cost element reports
- C. Structure information system reports
- D. Hierarchical reports
Answer: A,C
NEW QUESTION 60
To which object can you assign a factory calendar?
- A. Network header
- B. Milestone
- C. Relationship
- D. Material component
Answer: A
NEW QUESTION 61
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
- A. Assign a sales order to a project with appropriate hierarchy levels.
- B. Assign a network to a sales order
- C. Assign Several production orders to a sales order
- D. Assign One production order to a sales order
Answer: C
NEW QUESTION 62
......