NEW QUESTION 42
Which object is used to allocate the costs from a claim to the project structure?

  • A. WBS element
  • B. Internal order
  • C. Claim
  • D. Network activity

Answer: D

 

NEW QUESTION 43
You want to make sure that certain tasks must start on a given date. Where can you maintain constraints for start dates?

  • A. Milestone
  • B. Activity element
  • C. Network header
  • D. Activity

Answer: D

 

NEW QUESTION 44
Cost & Budget.
A customer wants to allocate overhead rates to a WBS element. What must you assign to the WBS element?

  • A. Investment profile.
  • B. Results analysis key
  • C. Costing Sheet
  • D. Settlement rules

Answer: D

 

NEW QUESTION 45
In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. The system automatically creates a new purchase requisition with the difference to the original quantity.
  • B. A workflow can be triggered to inform the purchasing group.
  • C. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO).
  • D. The purchase order is updated automatically to match the new quantity while saving the project.

Answer: B

 

NEW QUESTION 46
For which objects can billing plans be created? Note: There are 2 correct Answers to this question.

  • A. Project definition
  • B. WBS elements
  • C. Milestones
  • D. Sales order items

Answer: B,D

 

NEW QUESTION 47
To which object can you assign a factory calendar?

  • A. Milestone
  • B. Material component
  • C. Network header
  • D. Relationship

Answer: D

 

NEW QUESTION 48
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.

  • A. The maximum size of a free float is as large as the total float of an activity.
  • B. Float time can be negative.
  • C. By default, critical activities have a float time, which is less than or equal to zero.
  • D. Activities with the time constraint "Must start on" always have a negative float time.
  • E. The float time of WBS elements is calculated by extrapolation.

Answer: B,C,D

 

NEW QUESTION 49
You are working with networks and WBS elements. Which of the following statements applies

  • A. You can assign the network header to multiple WBS elements
  • B. You can reassign an activity from one network to another
  • C. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
  • D. You have to maintain a network profile in the project profile

Answer: C

 

NEW QUESTION 50
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

  • A. Standard network with activities
  • B. Assignment between material and standard network
  • C. A production order
  • D. A material master with sales views
  • E. A bill of material with sales views

Answer: A,B,D

 

NEW QUESTION 51
Which report can use user-specific layouts?

  • A. Cost element report
  • B. Line item report
  • C. Hierarchical report
  • D. Enhanced individual overview

Answer: D

 

NEW QUESTION 52
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Milestone trend analysis
  • B. Progress analysis
  • C. Settlement
  • D. Results analysis
  • E. Confirmations

Answer: B,C,D

 

NEW QUESTION 53
Which objects can be used to specify settlement rules? Note: There are 2 correct Answers to this question.

  • A. WBS elements
  • B. Network header for activity-account-assigned networks
  • C. Standard WBS elements
  • D. Network activity for activity-account-assigned networks

Answer: A,B

 

NEW QUESTION 54
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

  • A. Forward
  • B. Backward
  • C. Current date
  • D. Only capacity requirements

Answer: B

 

NEW QUESTION 55
Which of the following data can be maintained in a standard network? Note: There are 3 correct Answers to this question.

  • A. Relationships
  • B. Basic dates for activities
  • C. Internally processed activities
  • D. Material components
  • E. Document information records

Answer: A,C,D

 

NEW QUESTION 56
Project structure.
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?

  • A. You can use an indicator to determine that only coded project numbers may be used within the project system.
  • B. You can use only numbers for a project coding mask definition.
  • C. The standard project definition must differ from the definition of the operative project.
  • D. You can create project coding mask X... event if there are project numbers beginning with X.

Answer: A

 

NEW QUESTION 57
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?

  • A. Requirements type
  • B. Requirements class
  • C. Schedule line category
  • D. Item category

Answer: D

 

NEW QUESTION 58
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.

  • A. Resource reports
  • B. Cost element reports
  • C. Structure information system reports
  • D. Hierarchical reports

Answer: C

 

NEW QUESTION 59
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question

  • A. Resource reports
  • B. Cost element reports
  • C. Structure information system reports
  • D. Hierarchical reports

Answer: A,C

 

NEW QUESTION 60
To which object can you assign a factory calendar?

  • A. Network header
  • B. Milestone
  • C. Relationship
  • D. Material component

Answer: A

 

NEW QUESTION 61
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?

  • A. Assign a sales order to a project with appropriate hierarchy levels.
  • B. Assign a network to a sales order
  • C. Assign Several production orders to a sales order
  • D. Assign One production order to a sales order

Answer: C

 

NEW QUESTION 62
......