NEW QUESTION # 72
Test Management
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.
Which of the following answers would you expect to best describe how to organize the test plan?
Number of correct responses: 1
K3 2 credits

  • A. Produce four separate detailed level test plans, one for each level, without a master test plan
  • B. Produce a single master test plan that covers in detail all four levels, describing the particular activities for all test levels
  • C. Produce a master test plan that covers three levels (component, integration, system test) and a separate acceptance test plan
  • D. Produce a master test plan describing the relationship between the four levels, and four separate detailed level test plans, one for each level

Answer: D


NEW QUESTION # 73
Defect Management
Assume you are working on a defect management process to be used by a software organization to track the current status of the defects reports for several projects.
When a defect is found for investigation a defect report is created in "Opened" state that is the unique initial state. The defect report status has also a unique finale state that is the "Closed" state.
The following state transition diagram describes the states of this defect management process:

where only the initial ("Opened") and final ("Closed") states are indicated while the remaining states (V, W, X, Y, Z) have yet to be named.
Which of the following assignments would you expect to best complete the defect management process?
Number of correct responses: 1
K3 2 credits

  • A. V=Assigned, W=Validated , X=Corrected, Y=Re-Opened, Z=Rejected
  • B. V=Assigned, W=Corrected , X=Validated, Y=Re-Opened, Z=Rejected
  • C. V=Rejected , W=Corrected , X=Validated, Y=Re-Opened, Z=Assigned
  • D. V= Corrected, W=Assigned, X=Validated, Y=Corrected, Z=Rejected

Answer: B


NEW QUESTION # 74
Defect Management
Consider a defect report and assume that a part of its lifecycle includes the following states:
New: Is the initial state
Working: Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect
Closed: is the final state
Which of the following answers represents an invalid sequence of states that can't lead the bug report to the "Closed" state?

  • A. New, Working, Clarification, Working, Verification, Closed
  • B. New, Working, Verification, Closed
  • C. New, Working, Verification, Working, Clarification, Working, Verification, Closed
  • D. New, Working, Verification, Working, Clarification, Working, Closed

Answer: D


NEW QUESTION # 75
Assume that no additional product risks have been identified during the first week of test execution.


Which of the following answers would you expect to best describe the residual risks associated with the identified product risks, at the end of the first week of test execution?

  • A. Since R3 is the only risk for which all test cases have passed, the risk has been reduced by 20%
  • B. The test execution table doesn't give an indication of the risk level of the open defects and the test cases that failed or are not run yet
  • C. The residual risk level can't be determined, because it requires that all the test cases have been executed
  • D. The test execution status table indicates that the risk has been reduced by 56%

Answer: B

Explanation:
Section: Testing Process


NEW QUESTION # 76
What is a "depth-first" risk-based testing technique? [1]

  • A. Non-functional test cases are executed first
  • B. Lowest risk test cases are executed first
  • C. All risk items are tested at least once
  • D. Highest risk test cases are executed first

Answer: D

Explanation:
A depth-first risk-based testing technique is a method of prioritizing and executing test cases based on the risk level of the features or functions to be tested. In this technique, the test cases with the highest risk are executed first, followed by the test cases with lower risks. This ensures that the most critical and likely areas of failure are tested thoroughly and early in the testing process. Risk Based Testing: Approach, Matrix, Process & Examples - Guru99 References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, [Analytical Test Strategy: A Comprehensive Guide - LambdaTest]


NEW QUESTION # 77
Test Tools and Automation
Assume you are the Test Manager in charge of independent testing for avionics applications.
You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):
- a BOOT-X CSCI that must be certified at level B of the DO-178B standard
- a DIAG-X CSCI that must be certified at level C of the DO-178B standard
- a DRIV-X CSCI that must be certified at level A of the DO-178B standard These are three different software modules written in C language to run on a specific hardware platform.
You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.
Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C-compiler).
The source code of the tool is available.
Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.
Which of the following are the three main concerns related to that open-source tool selection?
Number of correct responses: 3
K4 3 credits (2 credits out of 3 credits correct, 1 credit point)

  • A. What are the costs to qualify the tool as a verification tool under the DO-178B?
  • B. Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?
  • C. Is the installation procedure of the tool easy?
  • D. Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-178B standard?
  • E. Does the tool have a good general usability?
  • F. Does the tool require a system with more than 4GB of RAM memory?

Answer: A,B,D


NEW QUESTION # 78
A chart showing the trend in the lag time from defect reporting to resolution during system testing is also available. The chart shows that the daily closure period is consistently and significantly above the rolling closure period for a long period of the system testing phase.
Almost all defects found during system testing have been related to the system as a whole, not related to single units or integrations issues. Almost all quality risks have been addressed during the unit and integration testing phase and no residual quality risks were present in the integrated system. This has been confirmed by exploratory testing sessions performed during system testing, targeted at finding defects in these quality risk areas.
Based on the given information only, which one of the following areas would you expect to be considered more in the retrospective meeting in order to be improved?
K3 3 credits

  • A. The requirements review
  • B. The system design and architecture design reviews
  • C. The quality risk analysis process
  • D. The defect management process

Answer: D

Explanation:
Topic 6, Test Tools and Automation


NEW QUESTION # 79
The following are the requirements identified as "critical":
REQ-SEL-001. The user shall be able to combine all the three products with all the four durations to define an item to purchase REQ-SEL-002. The user shall be able to add a maximum of six different items to the shopping cart REQ-PUR-001. The user shall be able to purchase all the items in the shopping cart using a credit voucher REQ-PUR-002. The user shall be able to purchase all the items in the shopping cart using the available credit already charged on the smartcard REQ-PUR-003. The user shall be able to purchase all the items in the shopping cart using all the accepted credit cards (Visa, MasterCard and Great Wall Card) REG-LOGO-001. The user shall be able to logout (by clicking the logout button) from both the "select" and
"purchase" pages going back to the "browse" page (anonymous navigation) Moreover the following quality risk item has been identified as "critical":
QR-P1. The web customer portal might not be able to provide the expected response time (less than 10 sec) for the purchase transactions under a load of up-to 1000 concurrent users Test analysis for system testing has just begun and the following test conditions have been identified:
TC-SEL-01. Test the combinations of products and durations to define an item to purchase TC-SEL-02. Test the maximum number of items, which can be added to the shopping cart TC-PUR-01. Test the purchase of an item TC-PUR-02. Test the purchase of an item with the credit charged on the smartcard Assume that you have used traceability to determine the logical test cases that cover all the requirements and the single risk item identified in that scenario.
Which of the following is a positive logical test that is complete, is correct, and covers the REG-LOGO-001 requirement?

  • A. On the purchase page ("purchase state"), click the logout button; verify that the browse page ("browse state") is displayed
  • B. On the browse page ("browse state"), click the logout button
  • C. On the select page ("select state"), click the logout button
  • D. On the purchase page ("purchase state"), click the logout button; verify that the "Impossible to logout - complete or cancel the current transaction" message is displayed

Answer: A

Explanation:
Section: Testing Process
Explanation/Reference:


NEW QUESTION # 80
Testing Process
Which of the following is an example of the test closure activity indicated as "lessons learned"?
Number of correct responses: 1
K2 1 credit

  • A. Archive all the test results of the acceptance testing phase
  • B. Participate in a meeting at the end of a project aimed at better managing the events and problems of future projects
  • C. Deliver a list of the open defects of a software product released into production to the service desk team
  • D. Deliver an automated regression test suite, used during the system test phase of a software product released into production, to the team responsible for maintenance testing

Answer: B


NEW QUESTION # 81
People Skills - Team Composition
Your test team consists of four members (Mary, Bob, Mark, Dave) with different interpersonal skills.
The following skills assessment spreadsheet shows the characteristics of the team members with respect to a list of interpersonal-skills (for each characteristic only the member with the highest level of that characteristic is indicated and marked with 'X'):

On the next project a member of your test team will have to perform some routine tasks requiring collaboration with other teams.
Who in your test team would you expect to be most suitable at doing these tasks?
Number of correct responses: 1
K43 credits

  • A. Mary
  • B. Bob
  • C. Dave
  • D. Mark

Answer: A


NEW QUESTION # 82
Test Management
The following chart plots the cumulative number of defects opened against the cumulative number of defects closed during system testing of a software product.

Which of the following statements is true?

  • A. The chart seems to indicate that the defect management process is not working well
  • B. The chart can be used to reveal test progress problems
  • C. The chart seems to indicate that the defect management process is working well
  • D. The chart indicates that you have plenty of problems left to find

Answer: C


NEW QUESTION # 83
Which technique will assist you in determining targeted improvement areas to reduce the number of defects?
[1]

  • A. Test coverage assessment
  • B. Defect triage
  • C. Pareto analysis
  • D. Cost of quality analysis

Answer: C

Explanation:
The technique that will assist you in determining targeted improvement areas to reduce the number of defects is Pareto analysis. This is because Pareto analysis is a method of identifying and prioritizing the most significant causes of defects, based on the principle that 80% of the problems are caused by 20% of the causes.
By applying Pareto analysis, you can focus on the improvement areas that will have the most impact on reducing the number of defects. Pareto Analysis - ISTQB not-for-profit association References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, Pareto Analysis - ISTQB not-for-profit association


NEW QUESTION # 84
Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company. Currently the application is able to support a proper number of users assuring the required responsiveness. Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.
Which of the following tools would you expect to be the most useful at performing this evaluation?
K2 1 credit

  • A. Coverage tools
  • B. Performance tools
  • C. Static analysis tools
  • D. Test management tools

Answer: B

Explanation:
Topic 7, People Skills - Team Composition


NEW QUESTION # 85
Assume you are working on a CAS (Conditional Access System) for Pay-TV that allows the access, selection and transfer of services and media to authorized users. Authorized users can choose their services through different channels: Web Customer Portal, IVR (Interactive Voice Response), Call Centre and SMS. The system uses a Smart Card to receive and decrypt the broadcasted encrypted control words which allow decrypting pay-per-view TV. Every authorized user must have a Smart Card and a Set-Top Box to view the contents.
The following is an excerpt from the product risk analysis document: Both likelihood and impact have been rated on the following scale: (1 - Very low, 2 - Low, 3 - Medium, 4 - High, 5 - Very High).
The required test environment and code have been delivered. All test cases for each identified product risk item have been written and are ready to be executed. The Database used to contain the Smart Cards is empty and so only new Smart Cards can be used during test execution.
A Smart Card can only be activated if it has been previously pre-activated. This means the post-conditions for the execution of the test cases to test the pre-activation of the Smart Card are the pre-conditions for activation of the Smart Card.
Which of the following statements represents the most effective contribution of the stakeholders to the completion of the failure mode analysis table?

K4 3 credits

  • A. The aircraft pilot and the customer representative should contribute to assess the detection. The chief software engineer, the system architect and the expert tester should contribute to assess the priority.
  • B. The aircraft pilot is the only one qualified to contribute to assess the priority and thus should be assigned this task. The customer representative should contribute to assess the detection.
  • C. The aircraft pilot and the customer representative should contribute to assess the priority. The chief software engineer, the system architect and the expert tester should contribute to assess the detection.
  • D. The system architect and the chief software engineer should contribute to assess the priority. The expert tester is the only one who should contribute to assess the detection.

Answer: C


NEW QUESTION # 86
Which of the following would you expect to be most likely an example of a demotivating factor for testers?
K2 1 credit

  • A. The same regressions tests are manually executed by the same testers, for every product release, without regression test tools
  • B. The testers are assessed on whether and how often they detect important and critical failures
  • C. Test quality is measured by counting the number of customer/user reported problems.
  • D. The testers' recommendations to improve the system or its testability are adopted by the development team
  • E. The management asks the testers to be kept informed about the intensity, quality and results of testing

Answer: A,C


NEW QUESTION # 87
Improving the Testing Process
Consider the following statements describing the importance of improving the test process:
I. Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can't indicate or suggest improvement to areas of the development process II. Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system III. Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years IV. Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi Which of the following answers is correct?
Number of correct responses: 1
K2 1 credit

  • A. I., II. and III are true; IV. is false
  • B. I., II. and III. are false; IV. is true
  • C. I. and IV. are true; II. and III. are false
  • D. I., II., III. and IV are false

Answer: D


NEW QUESTION # 88
Test Tools and Automation
Assume you are the Test Manager in charge of independent testing for avionics applications.
You are in charge of testing for a project to implement three different CSCI (Computer Software Configuration Item):
- a BOOT-X CSCI that must be certified at level B of the DO-178B standard
- a DIAG-X CSCI that must be certified at level C of the DO-178B standard
- a DRIV-X CSCI that must be certified at level A of the DO-178B standard These are three different software modules written in C language to run on a specific hardware platform.
You have been asked to select a single code coverage tool to perform the mandatory code coverage measurements, in order to meet the structural coverage criteria prescribed by the DO-178B standard. This tool must be qualified as a verification tool under DO-178B.
Since there are significant budget constraints to purchase this tool, you are evaluating an open-source tool that is able to provide different types of code coverage. This tool meets perfectly your technical needs in terms of the programming language and the specific hardware platform (it supports also the specific C- compiler).
The source code of the tool is available.
Your team could easily customize the tool to meet the project needs. This tool is not qualified as a verification tool under the DO-178B.
Which of the following are the three main concerns related to that open-source tool selection?

  • A. What are the costs to qualify the tool as a verification tool under the DO-178B?
  • B. Is the licensing scheme of the tool compatible with the confidentiality needs of the avionics company?
  • C. Is the installation procedure of the tool easy?
  • D. Does the tool support all the types of code coverage required from the three levels A, B, C of the DO-
    178B standard?
  • E. Does the tool have a good general usability?
  • F. Does the tool require a system with more than 4GB of RAM memory?

Answer: A,B,D


NEW QUESTION # 89
People Skills - Team Composition
Which of the following would you expect to be most likely an example of a demotivating factor for testers?
Number of correct responses: 2
K2 1 credit

  • A. The same regressions tests are manually executed by the same testers, for every product release, without regression test tools
  • B. The testers are assessed on whether and how often they detect important and critical failures
  • C. Test quality is measured by counting the number of customer/user reported problems.
  • D. The testers' recommendations to improve the system or its testability are adopted by the development team
  • E. The management asks the testers to be kept informed about the intensity, quality and results of testing

Answer: A,C


NEW QUESTION # 90
Most managers in your company consider the efforts of your test team valuable, while others see comprehensive testing as an unnecessary cost overhead to the SDLC.
What action could the Test Manager take to quantify the value of testing to the organization? [3]

  • A. Determine the cost of external failures.
  • B. Develop metrics that illustrate planned and actual testing hours.
  • C. Demonstrate the role QA has in similar size organizations.
  • D. Review the Test Plan with the management team.

Answer: A

Explanation:
Determining the cost of external failures involves analyzing the impact of defects that escape into production.
This includes the direct costs associated with fixing the defects, as well as the indirect costs such as customer dissatisfaction, damage to the company's reputation, and potential loss of business. By quantifying these costs, the Test Manager can illustrate the financial benefits of comprehensive testing in preventing high-cost external failures, thereby demonstrating its value as an investment rather than a cost overhead.
References:The ISTQB Advanced Level Test Manager documents provide guidelines on how to establish and use metrics to measure the effectiveness and efficiency of the testing process, including the cost of quality and the Return on Investment (ROI) for testing activities. These references support the rationale behind choosing option C as the verified answer.


NEW QUESTION # 91
......