Microsoft 070-348 Exam Overview:
| Certification Vendor: | Microsoft |
|---|---|
| Exam Name: | Managing Projects and Portfolios with Microsoft PPM |
| Exam Number: | 70-348 |
| Certificate Validity Period: | Retired exam (previously contributed to MCSE certification validity rules at the time of issuance) |
| Exam Price: | $165 USD (varies by region) |
| Available Languages: | Simplified Chinese, Japanese, English |
| Related Certifications: | MCSE: Project and Portfolio Management |
| Real Exam Qty: | 40-60 |
| Passing Score: | 700/1000 |
| Exam Format: | Multiple Choice, Case Studies, Drag and Drop |
| Exam Duration: | 120 minutes |
| Recommended Training: | Microsoft Learn - Project and Portfolio Management |
| Exam Registration: | Pearson VUE Registration |
| Sample Questions: | ![]() |
| Exam Way: | Online proctored or onsite via Pearson VUE |
| Pre Condition: | Recommended experience with Microsoft Project Server or Project Online, and general project management knowledge. |
| Official Syllabus URL: | https://learn.microsoft.com/en-us/credentials/certifications/exams/70-348/ |
Microsoft 070-348 Exam Syllabus Topics:
| Section | Objectives |
|---|---|
| Topic 1: Manage portfolios and demand management | - Prioritize projects and proposals - Analyze portfolio scenarios and optimization |
| Topic 2: Perform reporting and business intelligence | - Analyze project and portfolio performance - Build and use reports in Project Server |
| Topic 3: Manage resources | - Resource pools and assignments - Capacity planning and utilization |
| Topic 4: Configure workflows and business processes | - Approval processes and governance - Enterprise project workflows |
| Topic 5: Implement Microsoft Project and Portfolio Management (PPM) solution | - Manage enterprise project structure and settings - Configure Project Server / Project Online environment |
Common Microsoft Managing Projects and Portfolios with Microsoft PPM Questions from Candidates
070-348 is passed with 700/1000, and the official exam fee is $165 USD (varies by region). Fixing these numbers early helps you set a measurable practice target.
Pearson VUE Registration: register for 070-348
The 070-348 exam contains 40-60 questions to complete in 120 minutes minutes. Rehearsing under the same limit on the PassExamDumps engine turns pacing into a trained habit.
Microsoft Learn - Project and Portfolio Management: Visit official page
Choose the version of Microsoft Managing Projects and Portfolios with Microsoft PPM you want, one, two, or all three, add it to the cart, and complete payment through the secure Credit Card checkout. The download link then arrives by email within about a minute, so your study starts without wasted time.
The package includes 48 practice questions for the 070-348 exam. The count is set through analysis of a large volume of data, so the set matches the scope of the real test without padding.
- Perform reporting and business intelligence ()
- Manage portfolios and demand management ()
- Implement Microsoft Project and Portfolio Management (PPM) solution ()
Divide your time according to each topic's weight.
Payment runs through the Credit Card system, a globally used online payment network. We never share your personal information with third parties without your permission, and we never send spam, so your details stay where they belong.
Recommended experience with Microsoft Project Server or Project Online, and general project management knowledge.
Microsoft Managing Projects and Portfolios with Microsoft PPM Sample Questions:
DRAG DROP
You are the administrator for an organization that uses Microsoft PPM.
Users must be able to create projects by using predefined templates.
You need to create a new Enterprise Project Template and make it available for users.
In which order should you perform the actions? To answer, move all of the actions from the list of actions to the answer area and arrange them in the correct order.
Correct Answer:

HOTSPOT
You are the project manager for a real estate management company. You are using
Microsoft Project to manage the development of a new restaurant. The schedule includes a task named Equipment delivery.
Your supplier states that they will start delivering stoves, refrigerators, and other equipment on June 9, 2016.
You need to modify the Equipment delivery task.
How should you configure the constraint for the task? To answer, select the appropriate option from each list in the answer area.
Correct Answer:

You are a project manager in an organization that uses Microsoft PPM. You create a proposal for a new project by entering values for the Name, Description, Proposed Cost,
Proposed Benefits, and Sponsor Name properties.
The PMO must be able to approve all project proposals that have a proposed cost above a certain threshold value.
You need to use a project approval workflow.
Which three objects should use? Each correct answer presents part of the solution.
- A. Project schedule templates
- B. Project Departments
- C. Phases and stages
- D. Enterprise Project types
- E. Project Detail Pages
Correct Answer: C,D,E 🗳️
This question requires that you evaluate the underlined text to determine if it is correct.
To review the resource engagements requested by a project manager, the resource manager can navigate to the Resource Requests page and accept or reject the requests.
Review the underlined text. If it makes the statement correct, select "No change is needed."
If the statement is incorrect, select the answer choice that makes the statement correct.
- A. Capacity Planning page.
- B. No change is needed.
- C. Manage Users page
- D. Resource Plan view in Microsoft Project
Correct Answer: B 🗳️
Explanation: Only visible for PassExamDumps members. You can sign-up / login (it's free).
You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases.
Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team.
You need to configure Microsoft PPM.
What should you do?
- A. Set the Publish field to No for all tasks that need the assignments to be hidden from the team members.
- B. Set up a new security category for the management team.
- C. Delete the assignments that are not ready to be published to the team members.
- D. Set the booking type to Proposed for all tasks that need the assignments to be hidden from the team members.
Correct Answer: D 🗳️